Quick Answer (TL;DR)

Get Ghar Naksa Pass from your plot’s municipality/ward before building — it approves your drawings against zoning, setbacks, ROW, FAR and the National Building Code. Bring Lalpurja + Char-killa + Thapad Napi + malpot clearance + citizenship and architect/structural drawings stamped by a NEC-registered professional (soil test for 3+ floors). Fee ~Rs 10–25/sq ft residential; timeline 30–90 days for a clean file; issued as Asthai (plinth) → Sthai (full) → Completion Certificate.

Start with facts, not drawings: Ask the ward for your plot’s zoning, FAR and road ROW before your architect draws. Designing first and checking setbacks later is the most expensive mistake.

What Is Ghar Naksa Pass?

Naksha = drawing, Pass = approval. The municipality’s sign-off that your proposed building complies with local bylaws (setbacks, height, coverage, FAR), road Right of Way (ROW), and seismic safety under the Building Act 2055. Construction without it is illegal — inspectors can impose a stop-work order, fine, or in serious cases demolition on the offending portion.

Who Issues It?

Since federalism, your municipality / rural municipality (not a central ministry) reviews, inspects and issues Naksa Pass via its engineering/building-permit section. KMC, Lalitpur, Bhaktapur, Pokhara, Butwal etc. each publish their own bylaws and fee schedules — hence requirements differ slightly.

  • KMC / Lalitpur / Butwal: Electronic Building Permit System (EBPS) online submission + tracking (e.g., lsmcebps.gov.np) — still needs physical verification
  • Smaller municipalities: in-person paper filing at the ward

When You Need It

  • New construction of any size (even a one-room structure)
  • Vertical addition (extra floor), horizontal extension, or major structural change
  • Rebuilding after demolition (demolition papers required)
  • Change of use (residential → commercial) where bylaws differ

Required Documents

Land & Ownership

LalpurjaLand ownership certificate — original + copy (Land Revenue Office)
Char-killaFour-boundary certificate — confirms plot boundaries (Survey Office)
Thapad NapiCertified field measurement map / trace map (Survey Office)
Malpot clearanceCurrent FY land-tax receipt — no outstanding dues
CitizenshipLandowner’s nagrikta (or company PAN + registration for institutional owner)
Road/ROW noteWard road clearance where required for narrow access / shared wall

Design & Professional

Architectural drawingsSite plan, floor plans, elevations, sections — at required scales (often 1:100 plans, 1:50 sections), stamped/signed by a NEC/CAAN-registered architect
Structural drawingsFoundation, column-beam, reinforcement + calculation report — from a licensed structural engineer (mandatory for 3+ floors)
Soil testFrom a geotechnical firm — required for 3+ floors (takes 1–2 weeks; influences foundation design)
Plumbing/sanitationWhere municipality requires it
POA (if needed)Notarised Power of Attorney if owner not applying; if abroad, attested at the Nepali Embassy
Avoid delays: Update old Lalpurja/Char-killa data before applying — mismatches between Lalpurja plot area and the trace map vs drawings are the #1 correction reason.

Step-by-Step Process

  1. Pre-consult at the ward: take Lalpurja to confirm zoning, FAR, setbacks, height limit and any planned road widening that could affect ROW.
  2. Engage a registered professional: drawings by an unlicensed draughtsman are rejected outright.
  3. Prepare drawings + documents: ensure title blocks, plot area, road width, setbacks, floor areas and structural grids match across every sheet.
  4. Submit at the ward/municipality: via EBPS online where available (KMC/Bhaktapur/Lalitpur/Butwal) or in person; pay the initial application fee (built-up-area based) and get an acknowledgement slip with an application number.
  5. Document & design review: municipal engineers check bylaws + National Building Code; you may receive a written correction notice.
  6. Site inspection: engineer visits the plot to verify boundaries, access and existing structures against the survey map.
  7. Approval → collection: collect the stamped approved drawing set + permit (keep originals on site — inspectors check them).

Asthai vs Sthai Permit

Asthai Ijazat (Temporary)Issued after initial approval — authorises construction up to plinth / DPC level only
Plinth inspectionMunicipality confirms the plinth matches approved drawings
Sthai Ijazat (Permanent)Clears the superstructure; you may then complete the building
Nirman Sampanna (Completion)Final inspection after construction → Completion Certificate (needed for final bank disbursement, utility connections, future sale/insurance)

Fees

ResidentialCommonly quoted ~Rs 10–25 per sq ft of built-up area — municipality-dependent estimate as of October 2026; confirm the current rate paper at your municipality's revenue counter
CommercialCommonly quoted up to ~Rs 45 per sq ft — estimate; confirm locally
Revision after approvalAdditional fee to review an amended drawing (extra floor/area/structure)
Professional feesArchitect + structural engineer design fees separate; soil test fee separate (1–2 weeks, geotechnical firm)

Because fees track built-up area and use, a 2-floor house and a 4-floor apartment on the same plot pay very differently. Confirm the current rate per sq ft at your municipality’s revenue counter before budgeting and include it as a separate line in your House Construction Cost estimate.

Timeline

Official windowCommonly cited as 35 working days under the Local Government Operation Act — confirm the current provision text; practice varies
1–2 floor residential (clean file)Commonly reported 3–6 weeks (estimate)
3–5 floors (structural review)Commonly reported 6–10 weeks (estimate)
Heritage zones (Durbar Square etc.)Commonly quoted 10–16 weeks+ (unverified — confirm with the heritage desk)
Per correction roundCommonly +3–6 weeks (estimate)
KMC EBPS (clean, no conflicts)Sometimes reported as ~25–30 days for online-tracked files — confirm the current published turnaround at KMC

Inspections During Construction

  • Keep approved drawings on site — inspectors compare them directly to the structure
  • Expect inspections at plinth/DPC and at mid-construction; notify the office as required
  • Any setback/FAR/height deviation needs a formal revised Naksa Pass before building — building past an unpassed inspection is built at risk

Common Mistakes to Avoid

  • Starting excavation/foundation before the permit (stop-work/fine risk)
  • Measuring setback from the visible road edge instead of the official ROW (ROW is often wider)
  • Plot area differing across Lalpurja vs trace map vs drawings
  • Missing joint-owner consent or old demolition papers for a rebuild
  • Architectural vs structural drawings inconsistent (grid, floor area, stair)
  • Submitting without a soil test where required, or with a generic report not tied to your plot
  • Changing the design during construction without a revised permit

Checklist

  • Lalpurja, Char-killa, Thapad Napi, malpot receipt — area and plot number consistent
  • Citizenship + ward road/FAR/zoning confirmation
  • Architect + structural engineer engaged (NEC-registered) + soil test if 3+ floors
  • Drawings with consistent title blocks, scales and area tables
  • EBPS online submission where available + acknowledgement slip saved
  • Site inspection attended; Asthai → plinth inspection → Sthai → keep set on site
  • Completion Certificate applied for after construction

Official Sources & Final Note

Sources: Building Act 2055, National Building Code, Local Government Operation Act 2074 (35-day rule), and your municipality’s building bylaws + EBPS portal (e.g., lsmcebps.gov.np for KMC). Document lists and fees change by municipality — confirm at your ward before printing.

Last updated: September 27, 2026. Bylaws and fee schedules are revised periodically. Verify the current checklist at your municipality’s building-permit desk. SolutionsNepal is an educational guide, not the municipality.

Frequently asked questions

What is Ghar Naksa Pass?

The municipality’s approval of your building drawings — confirming zoning, setbacks, FAR, road ROW and National Building Code compliance before you build. Without it, construction is unauthorised; banks won’t mortgage, and the municipality can fine or stop work.

Where do I apply?

At the ward office / municipality’s building-permit section where your plot lies (KMC, Lalitpur, Bhaktapur etc. each have their own bylaws and EBPS portal). Start with the ward for zoning/FAR/road-width confirmation before commissioning drawings.

What documents are required?

Lalpurja + Char-killa + Thapad Napi (Survey Office), malpot tax clearance, citizenship, architectural + structural drawings stamped by a Nepal Engineering Council-registered professional, and soil test for 3+ floors. Heritage zones add extra review.

Can I apply online?

Partially — KMC, Lalitpur and some other municipalities operate an Electronic Building Permit System (EBPS) for online submission/tracking. Portal domains change (lsmcebps.gov.np is widely cited for Lalitpur — verify the live link on your municipality's website before using it); physical verification + site inspection + final collection remain offline.

How much does it cost?

Charged per sq ft of built-up area by the municipality: commonly quoted as ~Rs 10–25/sq ft residential, up to ~Rs 45/sq ft commercial — but these are unattributed estimates as of October 2026, not a named municipality schedule. Confirm the current per-sq-ft rate paper at your ward's revenue counter before budgeting.

How long does it take?

The Local Government Operation Act is commonly cited as setting a 35-working-day decision window — confirm the current provision text. In practice, clean residential files are reported as 30–90 days (KMC/Lalitpur timelines vary by EBPS queue — confirm the current published turnaround at your municipality). Heritage-zone reviews take longer (10–16 weeks is commonly quoted but unverified — confirm with the heritage desk). Incomplete files add weeks per correction round.

What is Asthai vs Sthai?

Asthai (temporary) permit lets you build up to plinth/foundation; after plinth inspection you get Sthai (permanent) permit for the superstructure. A final Completion Certificate closes the process after construction.

Can an NRN apply from abroad?

Yes via a notarised Power of Attorney authenticated at the Nepali Embassy, authorising a trusted person to submit, pay, and attend the site inspection.

Put this guide to work — every SolutionsNepal tool is free and needs no signup.

House Construction CostEstimate house construction cost in Nepal by location, size, floors and qualityOpen tool Construction Material CalculatorEstimate cement, sand, aggregate, bricks and steel quantities for construction in NepalOpen tool Land Affordability CalculatorFind how much land you can afford based on income, savings and loan EMI in NepalOpen tool Ropani → AanaConvert Ropani to Aana unitsOpen tool
Written by SolutionsNepal Team

Nepal property and municipal researchers